News 2005

 

 

Updates

 

01.03.2005

25.06.2005

 

25.06.2005

Jobs clash paralyses Sondu power project

The Standard
Saturday June 25, 2005

By Alphayo Otieno

A week after Japan expressed interest in funding another power plant at Sondu-Miriu, a fresh jobs controversy has paralysed work at the multi-billion power project.

Hopes that the project at the foot of Nyabondo Plateau would light up the neighbourhood have been replaced by uncertainty.

For the past four days, operations at the site have been grounded following a sharp disagreement between the contractors and the locals, who argue that some foreigners have been favoured for jobs they could handle.

Bloody demonstrations have now forced the project implementers to close shop temporarily.

Emotions ran high at a crisis meeting convened by Nyando District Commissioner John Egesa to iron out the differences.

A councillor, Simeon Akatch, claimed that the contractor had unfairly denied the locals jobs.

The remarks caused a sharp disagreement between the civic leader and the DC, who barred journalists from recording briefings by former Nyakach MP Ondiek Chillo.

Akatch blamed H-Young, a contractor, and the Kenya Electricity Generating Company (KenGen) community liaison officer, Mr Erick Oluoch.

"I was accosted by some workers who claimed they had been denied jobs and when I asked Oluoch about it, he said workers who had been ferried to the site had only come to assess work, materials needed and prepare a bill of quantities before returning to Nairobi," said Akatch.

But Mr Justus Waimiri, a public relations officer for KenGen, said those who had been employed at the site were experts, and that the locals had no reason to complain.

"The locals were mainly needed for the civil works which were not specialised and now there is no room for them," said Waimiri by phone.

The project has been plagued by problems since conceptualisation in 1985 to inception in 1999.

When it came back on course this year, Japan, its main financier, was optimistic that it would be ready by 2007 as scheduled.

Environmentalists and lobby groups, who argued that the project posed serious health and environmental risks to the residents, forced work to be suspended in 2002 at the end of the first phase.

Things got worse when the Japanese government tied the project’s financing to the World Bank and IMF conditions, asking Kenya to rein in rampant corruption.

Shortly after the Japanese move, President Kibaki travelled to Japan to renegotiate funding for Sondu-Miriu and other projects.

He returned with good news — that the project, which was fast becoming a white elephant, was headed for completion.

Last week, reports that another power project was in the horizon elicited excitement in the region.

Executives from the Japan Bank for International Co-operation (JBIC) toured the site of another power plant and expressed optimism that Japan would release funds for it.

"We are pleased with the administration of funds for the first and second phases of the first power plant project and we are considering funding another one here," said Mr Yoshiko Morita, JBIC chief executive.

Only two years ago, a senior JBIC official, Mr Katsumori Sawai said Japan had developed cold feet because of Kenya’s poor record in serving international debts.

The worst came when the Japanese Ambassador to Kenya, Mr Morshisa Aooki, threatened to cancel involvement in the project altogether.

Like the first power plant, the second power plant is likely to be handled by a Japanese contractor. Morita said a loan for the second power plant would be given on condition that only Japanese companies are awarded the major civil tenders.

He said the Japanese had drafted soft terms for the loan and it would only be fair for their companies to benefit.

In the first power plant, Konoike, the lead contractor, is undertaking civil works jointly with Viedekke Heavy Construction of Norway and Murray and Robberts Contractors International of South Africa.

Other companies are involved in the hydro-mechanical works, supply of generating equipment and construction of the transmission line.

KenGen awarded the design and supervision contract to Nippon Koei Company of Japan and the first construction contract to Konoike consortium.

The first and the second power plants are expected to add some 60 and 20 Megawatts to the national grid, operating at an annual energy output of 331 GWh.

A technical committee comprising JBIC and KenGen officials at the project last week said phase two of the first power plant was on course.

Phase two of the first power plant, which President Kibaki commissioned in March, was expected to cost Sh9.4 billion but the cost increased by Sh2 billion when the project stalled. Kengen is expected to provide the Sh2 billion and Japan Sh9.4 billion.

The resumption of work on the phase two of the project was delayed after the Japanese contractors failed to agree with KenGen on who would handle the difference after costs went up.

Sources indicated that the demands by Konoike Construction JV of Japan that KenGen pays a Sh10 billion penalty for breach of contract during the project’s phase one was to blame for the delay of phase two.

The contractors are said to have been demanding that civil works, hydro-mechanical, generating equipment and transmission line contracts be varied by between 70 to 80 per cent given the escalated cost of equipment over the three year period that worked stalled.

With construction work back on track, the second phase is expected to end by 2007. It is estimated that Sh1.8 billion out of the 9.4 billion will cater for engineering services and other contingencies.

KenGen deputy Managing Director Joe Ng’ang’a says the figures have been renegotiated to cater for the time lapse and economic parameters that have changed.

Ng’ang’a says it is likely that the project could be completed on time and within the budget.

 

01.03.2005

Japan threatens to withhold aid over graft claims


By JOHN OCHIENG
01. March 2005

President Kibaki is conducted on a tour of Sondu Miriu Hydro-Electric Power Project by KenGen managing director Eddy Njoroge shortly before he launched it yesterday.
Photo by PPS

Japan yesterday added its voice to the raging debate on corruption in Kenya when its envoy told President Kibaki: "Fight corruption or we'll not fund projects in Kenya."

The Japanese ambassador, Satoru Miyamura, spoke at Sondu Miriu hydropower project where the Head of State was officially launching the second phase of the multi-billion-shilling project.

The envoy told the President, to his face, that unless he showed satisfactory commitment to fight graft in his Government, Japan would stop funding projects in the country.

The envoy expressed Japan's displeasure with the Kenyan Government over alleged mass corruption among top Government officials and challenged the President to take decisive action to restore donor confidence.

Said he: "Japan is willing to fund more development projects here, but the allegations of corruption are holding us back. We will consider giving more support only if you put proper policies in place to weed out this vice from your Government."

But when he rose to speak, the President did not respond to the envoy's remarks and instead thanked the Japanese Government for resuming funding for the project's second phase, which stalled four years ago.

He said the project was an important component of the Government's strategy to reduce the growing energy demand in the country that has been increasing at the rate of 5 per cent per annum.

"This project is key to the success of my Government's economic recovery programmes. Most crucial is the electrical energy, which is essential for the functioning of the industrial sector," he noted.

It stalled when Japan withheld funding and gave tough conditions before resuming.

Also present during the groundbreaking ceremony were First Lady Lucy Kibaki and several Cabinet ministers. 

Work should have restarted earlier, but was delayed due to evaluation of costs, which increased during the period it stalled. It will now cost an extra Sh2 billion, which is to be met by the Kenyan Government through Kenya Electricity Generating Company (KenGen). 

The four contracts - for civil works, hydro mechanical works, generating equipment and transmission lines - and substations, signed between KenGen and various contractors, are worth Sh7.6 billion. In total, the project's second phase will cost Sh9.4 billion. Approximately Sh1.8 billion will cater for engineering services from phase one and other contingencies. The figures were renegotiated between the parties to cater for lapse of time and changed economic parameters. 

The project has been plagued by problems ranging from environmental, social to funding since its inception five years ago. As a result, it stalled at the end of the Sh14billion first phase in 2002 after the Japanese Government - the project's main donor withheld Sh7 billion funding for the second and final phase until certain conditions are met. (PPS)

 

 

OGIEK HOME